Market intelligence for the peptide supply chain
Market Data

Capacity Tracker

Tracking peptide manufacturing and upstream raw-material capacity projects worldwide.

Tracked
29
Projects / platforms
Peptide APIs
24
Manufacturing
Raw Materials
4
Upstream
Countries
10
Countries represented
Status
Operating / Commissioned9
Under Construction10
Announced / Planned10

Includes 1 peptide-development group. Groups are projects or platforms, not individual factories.

Research cutoff · October 9, 2026

Showing 29 of 29 groups

Approved peptide supply-chain projects and platforms. Expand qualifications for capacity definitions and limitations.
CompanyLocation / projectCapacity / capabilityStatusExpected milestoneSupply Model
Suzhou Highfine BiotechUpstream raw materialsSource ↗Huai'an phase-one reagent manufacturing project, JiangsuChina5130 tonnes/year (planned design)Upstream materials
Qualifications

Expected milestone: Q4 2026–Q1 2027 — first five workshops' trial production (company guidance)

Project-level construction; trial production, commercial production and product-line readiness are not confirmed. Review 2026-10-09: Trial guidance remains Q4 2026–Q1 2027 for first five workshops; no product mapping or commercial production confirmation.

Whole phase-one total. Includes 290 tonnes/year protected amino acids, 2,500 coupling reagents and 800 protection reagents. Components are subsets, not additional projects or quantities.

August 25 guidance is subject to construction progress. Window covers the first five of ten workshops, without product allocation; full-project startup unresolved.

Under ConstructionQ4 2026–Q1 2027UndeterminedAvailability: Undisclosed
Neuland LaboratoriesPeptide APIsSource ↗Bonthapally, Telangana — Module One and proposed Module TwoIndia7000 L (combined reactor volume)API synthesis
Qualifications

Module One reported operational September 15, 2026; utilization and customer-specific qualification undisclosed. Module Two remains proposed. Review 2026-10-09: Recovered company original: Module One operational at 7,000 L. Earlier 6,370 L unreconciled. Module Two up to 18,000 L remains proposed with no startup date.

Module One: 750 L SPPS + 6,250 L LPPS. Earlier 6,370 L specification remains unreconciled. Module Two up to 18,000 L is prospective, not additional operating capacity. Reactor volume is not annual API output.

Module Two startup undisclosed. Engineered >100 kg/year claim has unresolved module/scope and is not treated as demonstrated output.

Operating / CommissionedNot establishedCDMOAvailability: Undisclosed
Blue Jet HealthcareUpstream raw materialsSource ↗Vizag / Visakhapatnam — mixed-use manufacturing projectIndiaNot disclosedUpstream materials
Qualifications

Company reported engineering/preconstruction and consent to establish; peptide commissioning unverified. Review 2026-10-09: Site groundbreaking does not prove peptide-fragment construction or commissioning. Preserve planned peptide status.

Peptide fragments/intermediates prioritized; peptide-specific capacity undisclosed. Mixed-project investment is not peptide capacity.

August 3 management guidance concerns prospective commercialization around end-FY2029–FY2030, not a verified commissioning date.

Announced / PlannedNot establishedUndeterminedAvailability: Undisclosed
Anthem BiosciencesPeptide APIsSource ↗Unit IV, Harohalli, KarnatakaIndiaNot disclosedAPI synthesis
Qualifications

Company website reports construction; its publication date is undisclosed.

Peptide-specific capacity undisclosed. Separately commissioned Unit III and its 16 kL disclosure are excluded from this entry.

Under ConstructionNot establishedCDMOAvailability: Undisclosed
CordenPharmaPeptide developmentSource ↗Flatiron Park, Boulder, Colorado — development laboratoryUS64000 sq ft (laboratory floor area)API synthesis
Qualifications

Laboratory expansion announced; operations not verified.

Supporting peptide development space, not commercial API manufacturing volume or annual output.

Announced / PlannedNot establishedCDMOAvailability: Undisclosed
Lupin Manufacturing SolutionsUpstream raw materialsSource ↗Dabhasa, Gujarat — peptide building-block expansionIndiaNot disclosedUpstream materials
Qualifications

Expansion announced; commissioning not verified. Review 2026-10-09: Protected amino-acid expansion remains relevant; latest report supplies no quantitative product capacity or verified startup.

Protected-amino-acid capacity not quantified.

Announced / PlannedNot establishedUndeterminedAvailability: Undisclosed
CordenPharma / AmbioPharmPeptide APIsSource ↗North Augusta, South Carolina — former AmbioPharm expansionUS68000 sq ft (expansion floor area)API synthesis
Qualifications

Expected milestone: Early 2028 — company editorial indexed text; full-page confirmation pending

September 22 company groundbreaking; commissioning unverified. Acquisition completed in August and adds no new physical capacity. Review 2026-10-09: September 28 company editorial indexed text gives early-2028 go-live, later than June end-2027. Full-page access failed: qualified timing update only. Preserve USD118.96m / USD121.9m and later >USD200m scope differences; same 68,000 sq ft project and acquisition history.

One expansion originated by AmbioPharm. Floor area is not peptide output capacity. Investment disclosures have unresolved scope/budget differences.

June 16 state guidance; meaning of online is unspecified and was not reconfirmed in September. No exact startup date established. Earlier end-2027 guidance preserved as history; no exact commercial-production date.

Under ConstructionEarly 2028CDMOAvailability: Undisclosed
BachemPeptide APIsSource ↗Building K, BubendorfSwitzerlandNot disclosedMixed
Qualifications

Company reports commercial GMP manufacturing and ramp-up; full utilization not established. Review 2026-10-09: July company update confirms commercial GMP manufacturing/ramp; April inauguration is a separate milestone.

Peptide-only quantitative capacity undisclosed.

Operating / CommissionedNot establishedCDMOAvailability: Undisclosed
Chengdu Shengnuo BiologicalPeptide APIsSource ↗Dayi County, Sichuan — GLP-1 API industrialization projectChinaNot disclosedAPI synthesis
Qualifications

Company-reported construction; project commissioning and final permitting unverified.

June EIA describes 10 tonnes/year added after completion; October 2025 announcement describes >10 tonnes/year total with existing lines. Scope unresolved; neither is operating output. Other ramping workshops are not this project.

Under ConstructionNot establishedCDMOAvailability: Undisclosed
Nantong Changyou Pharmaceutical TechnologyPeptide APIsSource ↗Rudong / Nantong — semaglutide and tirzepatide projectChina140 kg/year (planned peptide-drug output)API synthesis
Qualifications

Construction/retrofit reported; commissioning and API-grade scope unverified.

120 kg/year semaglutide + 20 kg/year tirzepatide, planned. Non-peptide environmental acceptance does not establish peptide commissioning.

Historical May–July 2026 construction timetable is not a startup date. No peptide startup verified through October 7.

Under ConstructionNot establishedUndeterminedAvailability: Undisclosed
Medtide / Chinese Peptide Company / CPC ScientificPeptide APIsSource ↗Qiantang, Hangzhou — existing peptide API expansionChinaSeveral tonnes/year (company capacity claim)Mixed
Qualifications

Company manufacturing section reports commissioned as of June 30; introductory equipment-commissioning wording conflicts. Review 2026-10-09: Qiantang commissioned as of June 30 per September filing; actual output unquantified. Rocklin end-2026 up-to-300 kg/year target and new Qiantang phase-I property project are separate proposals.

Several tonnes/year is unquantified and not actual output. Up to 100 kg/batch is a separate capability. 3,000 L reactors are individual equipment scale, not a summed site volume. Rocklin and the separate proposed Qiantang phase I are excluded.

Operating / CommissionedNot establishedCDMOAvailability: Undisclosed
BachemPeptide APIsSource ↗Sisslerfeld / Eiken — planned first manufacturing phaseSwitzerlandNot disclosedAPI synthesis
Qualifications

Expected milestone: 2030 — company production-start guidance

Planned strategic collaboration; construction/operation not confirmed. Review 2026-10-09: Sisslerfeld customer-backed first-phase production target 2030; no annual output quantity.

Peptide-specific quantitative capacity undisclosed; investment is not output.

Company expectation, not a guaranteed or exact commissioning date.

Announced / Planned2030CDMOAvailability: Customer-committed
HRV Pharma / Arene LifesciencesPeptide APIsSource ↗India — dedicated Arene partner manufacturing arrangementIndiaNot disclosedAPI synthesis
Qualifications

Dedicated arrangement announced; completed scale-up and operating output unverified.

Arene owns/operates the capacity; it is not directly owned HRV capacity. Peptide-specific quantity and precise site unresolved.

Earlier March–May 2027 estimate remains unconfirmed; no verified startup date.

Announced / PlannedNot establishedUndeterminedAvailability: Customer-committed
Shilpa Medicare / Shilpa CDMOPeptide APIsSource ↗India — Shilpa CDMO peptide manufacturing platformIndiaNot disclosedAPI synthesis
Qualifications

Manufacturing details pending; no verified peptide commissioning milestone by October 7.

Peptide-specific quantitative capacity undisclosed. Broader small-molecule 230 kL is excluded.

CPHI publicity promised further details; this is not a verified plant startup date.

Announced / PlannedNot establishedCDMOAvailability: Undisclosed
Changzhou Pharmaceutical Factory / 常州制药厂有限公司Peptide APIsSource ↗Tianning Economic Development Zone, Changzhou, JiangsuChina380 kg/year (planned API capacity)API synthesis
Qualifications

Environmental approval received; commissioning/operation unverified.

280 kg/year fermentation-route semaglutide, 60 SPPS semaglutide, 40 tirzepatide. Tirzepatide route unresolved. Prospective capacity, not demonstrated output.

Startup depends on completion and operation of external industrial wastewater infrastructure; no date established.

Announced / PlannedNot establishedUndeterminedAvailability: Undisclosed
Sinopep / Jiangsu Sinopep-Allsino BiopharmaceuticalPeptide APIsSource ↗Lianyungang, Jiangsu — existing workshops 601/602China5779 kg/year (annual design capacity)API synthesis
Qualifications

Operating project reported by company; design capacity is not actual production or unrestricted merchant availability.

Rounded July 5.8-tonne claim and earlier Workshop 601 annual figures remain distinct/unreconciled. Historical 4.7% utilization denominator/period unresolved; no spare-capacity calculation.

Operating / CommissionedNot establishedCDMOAvailability: Undisclosed
Sunresin / 西安蓝晓科技新材料股份有限公司Upstream raw materialsSource ↗Pucheng, Weinan, Shaanxi — life-sciences manufacturing projectChinaNot disclosedUpstream materials
Qualifications

Planned project; approvals progressing. Construction/operation of peptide supports not verified.

Peptide solid-phase synthesis supports/resins included; peptide-specific capacity undisclosed. Whole-park 16,400 tonnes/year and investment are excluded. August resin scale-up is not established as Pucheng production.

May 20 company expectation of phased completion/production over approximately two years concerns the park; peptide-line startup undisclosed.

Announced / PlannedNot establishedUndeterminedAvailability: Undisclosed
Asymchem / 凯莱英Peptide APIsSource ↗Aggregate peptide platform / TJ4-linked and Tianjin TIDES projectChina>45000 L (commissioned reactor volume)Mixed
Qualifications

Aggregate baseline commissioned according to company. Separate Tianjin mixed-TIDES investment is under construction, not operational; relationship to baseline unresolved. Review 2026-10-09: Commissioned >45,000 L and separate >22.5 tonnes/year company claim retained; ~69,000 L is future total target reaffirmed August, not an incremental 24,000 L addition.

Separate >22.5 tonnes/year capability claim is not actual output or another project. ~69,000 L year-end target is a future total. Tianjin peptide-specific capacity undisclosed. Grouped to prevent overlapping entry/quantity counts.

~69,000 L by end-2026 is a capacity target, not a verified startup date. Tianjin project startup undisclosed.

Operating / CommissionedNot establishedCDMOAvailability: Undisclosed
Space Peptides (Taizhou) / 泰州兴普泰生物制药有限公司Peptide APIsSource ↗Taixing, Taizhou, Jiangsu — multi-year peptide expansionChinaNot disclosedAPI synthesis
Qualifications

Company-announced expansion; new construction commencement unverified.

>70,000 L SPPS and >30 tonnes/year are prospective company targets only. Earlier capacity figures/timelines remain unreconciled; target/API-grade scope uncertain. No additive building 2–4 entries.

Five-year plan is not an exact commissioning/startup date.

Announced / PlannedNot establishedCDMOAvailability: Undisclosed
Sichuan Jisheng Biopharmaceutical / 四川吉晟生物医药有限公司Peptide APIsSource ↗Phase II Building 2, Leshan High-tech Zone, SichuanChinaNot disclosedAPI synthesis
Qualifications

Line 3 construction reported in March; later startup remains unverified. Line 4 remains planned, not verified under construction.

Reliable line-specific quantitative capacity undisclosed. Conditional full-load/batch claims excluded. API qualification, products and parcel scope unresolved.

Line 3 end-April target elapsed without verified startup. Line 4 end-2026 remains company guidance, not an established startup date.

Under ConstructionNot establishedUndeterminedAvailability: Undisclosed
Cambrex / Cambrex Charles City, Inc.Peptide APIsSource ↗Charles City, Iowa — planned expansion including LPPSUSNot disclosedAPI synthesis
Qualifications

Initial engineering complete; construction commencement unverified through October 7.

Commercial-scale liquid-phase peptide manufacturing planned. Broader 140,000 L / USD120m figures are not peptide-specific. Peptide quantity and annual output undisclosed.

Late-2026 groundbreaking guidance is not verified commencement or an operational startup date.

Announced / PlannedNot establishedCDMOAvailability: Undisclosed
Eli LillyPeptide APIsSource ↗Lebanon, Indiana — API manufacturing siteUSNot disclosedMixed
Qualifications

Expected milestone: 2027 — company target for API-site opening

API site target opening 2027. Separate Advanced Therapies site opened May 2026. Investment spans sites and mixed API products; no peptide-specific quantity.

Company milestone/target; exact production eligibility or output not inferred.

Under Construction2027CaptiveAvailability: Captive
Eli LillyPeptide APIsSource ↗Kinsale — IE2b complex-peptide expansionIrelandNot disclosedAPI synthesis
Qualifications

Expansion began making medicines in 2023, inaugurated 2024. SPPS fragments plus continuous LPPS; no annual peptide capacity disclosed.

Company milestone/target; exact production eligibility or output not inferred.

Operating / CommissionedNot establishedCaptiveAvailability: Captive
Novo NordiskPeptide APIsSource ↗Kalundborg — 2023 API/packaging expansionDenmarkNot disclosedMixed
Qualifications

Expected milestone: 2029 — company fully-operational target

Multi-product API including GLP-1 plus packaging; expected fully operational 2029. Original >DKK42bn, latest DKK49.6bn whole-project budget, not capacity. Distinct earlier fermentation upgrade not additive.

Company milestone/target; exact production eligibility or output not inferred.

Under Construction2029CaptiveAvailability: Captive
WuXi STA / WuXi AppTecPeptide APIsSource ↗Company-wide peptide/SPPS platform; Changzhou, Taixing and SingaporeChina / Singapore>100000 L (aggregate SPPS reactor volume)Mixed
Qualifications

Aggregate >100,000 L SPPS at end-2025. Future 130,000 L target undated. Chinese site quantities not allocated; Singapore TIDES Q2 2028 target. Children are not additional public groups.

Company milestone/target; exact production eligibility or output not inferred.

Operating / CommissionedNot establishedCDMOAvailability: Undisclosed
CordenPharmaPeptide APIsSource ↗Colorado — commercial SPPS expansion, BoulderUS25000 addition; >42000 future total L (SPPS reactor volume; prospective)API synthesis
Qualifications

Expected milestone: 2028 — company target

25,000 L disclosed addition; >42,000 L future site total in 2028. Not additive to each other. Separate from CAP-2026-008 development laboratory floor area.

Company milestone/target; exact production eligibility or output not inferred.

Under Construction2028CDMOAvailability: Undisclosed
PolyPeptidePeptide APIsSource ↗Braine-l’Alleud — large-scale SPPS facilityBelgiumNot disclosedAPI synthesis
Qualifications

Started production December 2024; target utilization achieved H1 2026. Contract-backed facility; no inference of spare capacity or annual output. EUR100m investment/order value not physical capacity.

Company milestone/target; exact production eligibility or output not inferred.

Operating / CommissionedNot establishedCDMOAvailability: Customer-committed
PolyPeptidePeptide APIsSource ↗Malmö — SPPS doubling expansionSwedenNot disclosedAPI synthesis
Qualifications

Expected milestone: 2027 — company ramp target

Construction complete; commissioning ongoing as of H1 results. Ramp target 2027. Relative doubling not annual output; supported by customer contract, no exclusivity inferred.

Company milestone/target; exact production eligibility or output not inferred.

Commissioning2027CDMOAvailability: Customer-committed
PolyPeptidePeptide APIsSource ↗Strasbourg — SPPS expansionFranceNot disclosedAPI synthesis
Qualifications

Company reported expanded SPPS operational by March 12, 2026; H2 2026 ramp target. Relative doubling not annual output; exact startup date undisclosed.

Company milestone/target; exact production eligibility or output not inferred.

Operating / CommissionedNot establishedCDMOAvailability: Undisclosed

29 approved project/platform groups, including one development laboratory. WuXi site milestones remain within one aggregate platform; Highfine components and Asymchem’s overlapping disclosures are not counted as additive projects or capacity. Status reflects supported disclosures, not verified current utilization. Reactor litres, annual capacity claims, batch capability and floor area are different measures and must not be added. Captive and customer-committed capacity is not generally available merchant supply. “Not disclosed” does not mean zero. Commissioning is included under Under Construction in headline counts.

Peptide manufacturing milestones · 2026–2030

Selected manufacturing milestones. Reported achievements and company targets are shown separately; event counts are not additional project counts.

Reported achievedCompany target

2026

  1. Company target2026-Q4/2027-Q1

    Highfine · Huai’an first five workshops

    Trial production expected Q4 2026–Q1 2027, subject to construction progress; no product allocation

    Milestone qualifications

    Company target · Window · China · Undetermined

    Read description and confirmed/target field: site opening, reporting, trial production and ramp milestones are not interchangeable with validated commercial production.

    Source ↗ · View tracker group
  2. Reported achieved2026-09-15

    Neuland · Module One

    Module One reported operational: 7,000 L total reactor volume

    Milestone qualifications

    Company-reported achieved · Disclosure date; exact startup undisclosed · India · CDMO

    Read description and confirmed/target field: site opening, reporting, trial production and ramp milestones are not interchangeable with validated commercial production.

    Source ↗ · View tracker group
  3. Reported achieved2026-09-22

    CordenPharma / AmbioPharm · North Augusta

    Groundbreaking of existing expansion project; acquisition is not capacity addition

    Milestone qualifications

    Company-reported achieved · Day; baseline captured source · US · CDMO

    Read description and confirmed/target field: site opening, reporting, trial production and ramp milestones are not interchangeable with validated commercial production.

    Source ↗ · View tracker group
  4. Reported achieved2026-07-30

    Bachem · Building K, Bubendorf

    Commercial GMP manufacturing underway and ramping by July update; separate April inauguration

    Milestone qualifications

    Company-reported achieved · Disclosure by-date · Switzerland · CDMO

    Read description and confirmed/target field: site opening, reporting, trial production and ramp milestones are not interchangeable with validated commercial production.

    Source ↗ · View tracker group
  5. Reported achieved2026-04-14

    Asymchem · Aggregate peptide platform

    >45,000 L commissioned SPPS disclosed; reporting milestone, not April commissioning date

    Milestone qualifications

    Company-reported achieved · Disclosure date · China · CDMO

    Read description and confirmed/target field: site opening, reporting, trial production and ramp milestones are not interchangeable with validated commercial production.

    Source ↗ · View tracker group
  6. Company targetEnd-2026

    Asymchem · Aggregate peptide platform

    Approximately 69,000 L future total by year-end; no derived increment

    Milestone qualifications

    Company target · Year-end · China · CDMO

    Read description and confirmed/target field: site opening, reporting, trial production and ramp milestones are not interchangeable with validated commercial production.

    Source ↗ · View tracker group
  7. Reported achieved2026-06-09

    Asymchem · Tianjin TIDES project

    Government reports construction commencement; peptide quantity undisclosed

    Milestone qualifications

    Government-reported achieved · Day · China · CDMO

    Read description and confirmed/target field: site opening, reporting, trial production and ramp milestones are not interchangeable with validated commercial production.

    Source ↗ · View tracker group
  8. Reported achieved2026-06-30

    Medtide · Existing Qiantang

    Facility commissioned as of June 30 according to later September filing; actual output not quantified

    Milestone qualifications

    Company-reported achieved · As-of date; not exact commissioning date · China · CDMO

    Read description and confirmed/target field: site opening, reporting, trial production and ramp milestones are not interchangeable with validated commercial production.

    Source ↗ · View tracker group
  9. Reported achievedH1 2026

    PolyPeptide · Braine-l’Alleud

    Target utilization achieved H1 for existing commercial-production facility; not new commissioning

    Milestone qualifications

    Company-reported achieved · Half-year · Belgium · CDMO

    Read description and confirmed/target field: site opening, reporting, trial production and ramp milestones are not interchangeable with validated commercial production.

    Source ↗ · View tracker group
  10. Reported achievedH1 2026

    PolyPeptide · Malmö expansion

    Construction complete; commissioning ongoing as of H1 results

    Milestone qualifications

    Company-reported achieved · As-of half-year · Sweden · CDMO

    Read description and confirmed/target field: site opening, reporting, trial production and ramp milestones are not interchangeable with validated commercial production.

    Source ↗ · View tracker group
  11. Reported achieved2026-03-12

    PolyPeptide · Strasbourg expansion

    SPPS expansion reported operational by March 12; exact startup undisclosed

    Milestone qualifications

    Company-reported achieved · Disclosure by-date · France · CDMO

    Read description and confirmed/target field: site opening, reporting, trial production and ramp milestones are not interchangeable with validated commercial production.

    Source ↗ · View tracker group
  12. Company targetH2 2026

    PolyPeptide · Strasbourg expansion

    Ramp-up target in H2 2026

    Milestone qualifications

    Company target · Half-year · France · CDMO

    Read description and confirmed/target field: site opening, reporting, trial production and ramp milestones are not interchangeable with validated commercial production.

    Source ↗ · View tracker group
  13. Company targetEnd-2026

    Sichuan Jisheng · Fourth peptide line

    End-2026 fourth-line plan; construction/operation not verified

    Milestone qualifications

    Company target · Year-end · China · Undetermined

    Read description and confirmed/target field: site opening, reporting, trial production and ramp milestones are not interchangeable with validated commercial production.

    Source ↗ · View tracker group
  14. Company targetLate 2026

    Cambrex · Charles City

    Late-2026 groundbreaking target; engineering completion is not construction start

    Milestone qualifications

    Company target · Late-year guidance · US · CDMO

    Read description and confirmed/target field: site opening, reporting, trial production and ramp milestones are not interchangeable with validated commercial production.

    Source ↗ · View tracker group

2027

  1. Company target2027

    Eli Lilly · Lebanon API site

    API-site opening target; separate from Advanced Therapies inauguration

    Milestone qualifications

    Company target · Year · US · Captive

    Read description and confirmed/target field: site opening, reporting, trial production and ramp milestones are not interchangeable with validated commercial production.

    Source ↗ · View tracker group
  2. Company target2027

    WuXi STA · Taixing new TIDES plants

    Two new TIDES plants expected operational; peptide allocation undisclosed

    Milestone qualifications

    Company target · Year · China · CDMO

    Read description and confirmed/target field: site opening, reporting, trial production and ramp milestones are not interchangeable with validated commercial production.

    Source ↗ · View tracker group
  3. Company target2027

    PolyPeptide · Malmö expansion

    Expanded facility ramp-up target

    Milestone qualifications

    Company target · Year · Sweden · CDMO

    Read description and confirmed/target field: site opening, reporting, trial production and ramp milestones are not interchangeable with validated commercial production.

    Source ↗ · View tracker group

2028

  1. Company targetQ2 2028

    WuXi STA · Singapore TIDES

    TIDES component target Q2 2028; not general small-molecule 2027 date

    Milestone qualifications

    Company target · Quarter · Singapore · CDMO

    Read description and confirmed/target field: site opening, reporting, trial production and ramp milestones are not interchangeable with validated commercial production.

    Source ↗ · View tracker group
  2. Company target2028

    CordenPharma · Colorado commercial SPPS

    Future >42,000 L site total target, including disclosed 25,000 L addition

    Milestone qualifications

    Company target · Year · US · CDMO

    Read description and confirmed/target field: site opening, reporting, trial production and ramp milestones are not interchangeable with validated commercial production.

    Source ↗ · View tracker group

2029

  1. Company target2029

    Novo Nordisk · Kalundborg 2023 expansion

    Multi-product API/packaging expansion expected fully operational

    Milestone qualifications

    Company target · Year · Denmark · Captive

    Read description and confirmed/target field: site opening, reporting, trial production and ramp milestones are not interchangeable with validated commercial production.

    Source ↗ · View tracker group

2030

  1. Company target2030

    Bachem · Sisslerfeld first phase

    Production target for customer-backed first phase

    Milestone qualifications

    Company target · Year · Switzerland · CDMO

    Read description and confirmed/target field: site opening, reporting, trial production and ramp milestones are not interchangeable with validated commercial production.

    Source ↗ · View tracker group